Construction and rehabilitation of water supply system to main works for Tuy Hoa, La Hai and Chi Thanh, Phu Yen province – Transmission pipeline and Water processing Plant

Updated at 15/09/2011 10:29:00 AM (GMT+7)

Contract No.3/05/TCB/PY3: Construction and rehabilitation of water supply system to main works for Tuy Hoa, La Hai and Chi Thanh, Phu Yen province – Water transmission pipeline and processing Plant.

Project construction value: 85.827 Billion Vietnam dong

Implemented value by Viwaseen.2: 43.970 Billion Vietnam dong

Commencement date: November 2006

Completion date: September 2009

Employer: Phu Yen Province Water Supply and Environmental Sanitation PMU